Case Study · Housing · Porto and Braga
Quantities evidenced before the invoice arrives.
How CLK Engenharia in Portugal records quantities, construction progress and concealed work with the 360° walkthrough – week after week, across several sites at once.


Building shell in Porto: the walkthrough of 17 June as a 360° image and a 3D model you can measure.
Results
- 10 h → 2 h
- Site measurement per billing stage
- 5
- Construction sites at the same time in Plonda
- 1 ×
- Walkthrough per week and construction site
Starting point.
An interim payment application is submitted every month, and every item needs evidence. Previously this meant plans, phone photos and on-site measurements, often weeks after the work was completed. Work hidden behind suspended ceilings or screed could hardly be documented afterwards.
Use of Plonda.
Once a week, a site manager walks through each site with the 360° camera. Plonda records the condition and date, builds a 3D model in which areas can be measured, and links quantities to the bill-of-quantities items.

Extract from the bill of quantities
Original items from one project's bill of quantities, translated.
Result.
Measurements for a billing stage are taken at the desk instead of on site. Quantity discrepancies are found before approval rather than at the final invoice. And when a variation is disputed, the walkthrough from that day provides the evidence.

“With Plonda I go back in the walkthrough to the day the work was carried out and measure it. That ends most discussions before they begin.”
José Sá Machado, CLK – Construção e Engenharia · translated from Portuguese